Cost Codes

A cost code is the label that tells TrueGrade what a dollar was spent on — Concrete, Framing, Electrical Rough-In, Site Work, and so on. Your cost code library is the backbone of cost tracking: every estimate line, budget, invoice, and actual cost is assigned a code, which is what lets TrueGrade compare estimated vs. actual and roll costs up by category.

Cost codes are managed under Settings → Cost Codes. Only Admin and Platform Admin roles can change the library.

Structure

Most builders organize cost codes hierarchically:

03 - Concrete 03.10 - Formwork 03.20 - Reinforcement 03.30 - Cast-in-Place Concrete 06 - Wood & Plastics 06.10 - Rough Carpentry 06.20 - Finish Carpentry

You can build your own numbering or start from a standard construction cost-coding system (such as the CSI MasterFormat divisions) and adapt it.

Managing the Library

  • Add a code with a number, a name, and an optional parent code
  • Deactivate a code you no longer use — it stays on historical records but won’t appear for new entries
  • Import a full library from a spreadsheet when first setting up
  • Map each code to a QuickBooks expense account for accounting export

Avoid deleting a cost code that has already been used on estimates or actuals — deactivate it instead. Deleting a code in active use breaks the link between historical costs and their category.

Where Cost Codes Are Used

AreaHow cost codes appear
EstimatesEvery estimate line is assigned a code
Cost ActualsInvoices and receipts are coded as they’re entered
Budget ReportingCosts roll up by code for estimate-vs-actual comparison
QuickBooks ExportCodes map to expense accounts in your books

Getting Started

  1. Open Settings → Cost Codes
  2. Import your existing library or add codes one at a time
  3. Group codes under parents to match how you report
  4. Map codes to QuickBooks accounts if you export to accounting
  5. Save — the library is immediately available across estimates, actuals, and reports